Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

FURTHER PROGRESS UPDATE - NOTIFICATION OF ESSENTIAL MAINTENANCE WORKS A1 Apleyhead to Newark

By Cheryl Day Elkesley Parish Council

Thursday, 3 April 2025

ABOUT THE AUTHOR

Elkesley Parish Council Contributor

VIEW ALL ARTICLES BY THIS AUTHOR

I am writing to provide an update on the ongoing resurfacing of the A1 between Apleyhead (A57/A614 junction) and Newark (A17/A46 junction).

The scheme is progressing well. There will be no further work until Tuesday 6 May, when we begin Phase 3 on the A1 northbound carriageway.

We will continue to work Monday to Friday, from 8pm to 6am with a full closure in place on the A1 northbound carriageway from Newark to Markham Moor. A fully signposted diversion route will be place via the A56 and A47.I am writing to provide an update on the ongoing resurfacing of the A1 between Apleyhead (A57/A614 junction) and Newark (A17/A46 junction).

We continue to work Monday to Friday, from 8pm to 6am. The scheme is progressing well and we are now in Phase 2 until 28 March. Work is ongoing on the southbound carriageway, which remains fully closed from Markham Moor to Newark. A fully signposted diversion route is in place via the A57 and A46.

There will be no work between 29 March and 5 May. On 6 May we begin Phase 3 which is the first of two phases on the northbound carriageway.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

I am writing to provide an update on our progress as we resurface the A1 between its junction with the A57/A614 at Apleyhead and the A17/A46 at Newark. We continue to work Monday to Friday, between 8pm and 6am.

The scheme is progressing well despite some weather-related delays. While we have lost some shifts due to inclement weather conditions, we have allocated additional resources to mitigate the impact on our programme. We continue in Phase 1 with a full closure of the A1 southbound from Apleyhead to Newark. The fully signposted diversion route uses the A616 and A614.

On the evening of Wednesday 26 February we will move to Phase 2. We continue on the southbound carriageway with a full closure from Markham Moor to Newark. The diversion route will use the A57 and A46.

For an overview of this scheme with links to the diversion routes, please visit the National Highways website below and click on the A1 Apleyhead to Newark Resurfacing scheme.

https://nationalhighways.co.uk/our-roads/east-midlands/east-midlands-maintenance-schemes/

We are resurfacing the A1 between its junction with the A57/A614 at Apleyhead and the A17/A46 at Newark to give you a safer, smoother journey. I am writing to let you know that after a delayed start due to flooding, work will go ahead tonight as planned and dates for each phase may need to be updated as a result.

Work was initially carried out under lane or slip road closures but from this evening we will need full carriageway closures. To minimise disruption these will take place overnight from 8pm to 6am on Mondays to Fridays, in one direction at a time in the following phases:

Phase 1 - 13 January to 10 February – A1 southbound closure from Apleyhead to Newark

Phase 2 - 11 February to 12 March – A1 southbound closure form Markham Moor to Newark.

Phase 3 - 13 March to 28 March – A1 northbound closure from Newark to Markham Moor.

Phase 4 - 6 May to 11 July – A1 northbound closure from Newark to Apleyhead.